Feasibility Study in the Philippines: What It Covers, What It Costs, and When You Need One

By Rodel Lacorte, CPAAs of 30 October 2026

This guide summarizes the laws, guidelines and industry practice linked below, as viewed in October 2026. Requirements and fees change, so confirm with the agency or lender concerned and commission a study scoped to your project.

A feasibility study is the document that decides whether money moves. A bank, an investor or an approving body reads it to answer three questions: is there real demand, can this be built and run at the cost claimed, and does the cash come back with margin to survive a bad year?

I have sat on both sides of that table. Between 2008 and 2010 I put together three hydropower studies, including the Ibulao mini-hydropower project in Ifugao, and carried them through financial modelling and capital raising. The studies that moved forward were rarely the longest; they were the ones whose every assumption could be defended by someone who had stood on site.

What a feasibility study is, and what it is not

A feasibility study tests whether a project should exist. A business plan explains how an approved one will be run.

Feasibility studyBusiness plan
QuestionShould we do this, and at what scale?How do we execute it?
ReaderLenders, investors, boards, approving agenciesManagement and staff
DirectionTests the idea, and may kill itAssumes the decision is made
Ends withA recommendation and its conditionsTargets, budgets, calendar

A pre-feasibility study is the short version: secondary data, rough cost ranges and a screening model, used to decide whether a full study is worth paying for. A full study replaces estimates with priced quotations, site data, primary research and a complete model — the version a bank reads.

What Philippine rules require

No single statute fixes the contents of a private study. What exists is a set of agency requirements that differ by reader.

ReaderApplies toWhat it asks for
ICC, through DEPDev (the former NEDA)Major projects seeking approval, ODA or PPP structuringFinancial, economic, technical, institutional and social evaluation, plus sensitivity analysis
BOIRegistration for CREATE incentives20-year projections: income statement, payroll with headcount, overheads, depreciation, taxes, balance sheet, cash flow; plus three years of audited statements
PEZAEcozone registrationIts rules list a feasibility study but mark it no longer required; instead, basic technical, financial, marketing and management data
LandBankBusiness and project loansThree years of audited statements or pre-operating statements, plus a business plan; under the DOST-TAPI I-Tech channel it lends through, a feasibility study or project details for start-ups
DBPLGU and project financingFeasibility study or project description, with cost estimates and engineering documents
DHSUD, under PD 957Subdivisions, condominiumsA sworn registration statement with a balance sheet; the licence to sell turns on financial stability
DENR-EMB, under PD 1586Projects in EIS Categories A and BAn EIS or IEE checklist for an ECC, or a Certificate of Non-Coverage

Two of these set the real bar. For PPP projects, the PPP Code's implementing rules carry the most explicit content list in Philippine regulation. Section 19 requires objectives, project description, outcomes and KPIs with their assumptions, technical alternatives and risks, project cost, legal due diligence, demand and supply analysis covering competitors and barriers to entry, financial analysis consistent with the model, economic and social analysis, and risk allocation. The model must show the debt service coverage ratio, IRRs, net present values and the weighted average cost of capital.

For ICC review, the 2004 guidelines require a cash flow covering the whole project life plus the year before implementation, audited statements for at least the prior three years, and the major assumptions stated. A market study may be required, and it "should include a definition of the types and nature of the products/services to be generated by the program/project, their specific and potential markets, existing and projected demand and the resulting supply gaps." Public projects are also measured against a 10% social discount rate, cut from 15% in 2016.

The anatomy of a bankable study

SectionWhat goes in itWhat gets checked
1. Executive summaryRecommendation, capital, key returns, main risksWhether it matches the model
2. Background and proponentsThe opportunity, sponsors, track record, structureWho has done this before, who is liable
3. Market and demandSize, segments, competitors and shares, pricing, forecastWhether demand is built bottom-up
4. TechnicalSite, capacity, technology, utilities, manpower, schedule, capital costWhether capacity matches demand and cost is quoted
5. ManagementOwnership, board, key hires, org chart, payWhether the team is costed and named
6. Legal and regulatoryStructure, ownership limits, permits, land tenure, taxWhether the permits listed are the ones needed
7. Environmental and socialScreening category, ECC or CNC route, impacts, mitigation, consultationsWhether clearance is costed and scheduled
8. FinancialProject cost, sources and uses, projections, NPV, IRR, payback, break-even, DSCRWhether assumptions are traceable and debt is serviceable
9. RiskRisk register, allocation, mitigation cost, sensitivities, scenariosWhether the downside cases are realistic
10. ConclusionGo, no-go, or go with conditionsWhether the recommendation follows the analysis

The market study is where studies live or die

"The Philippine coffee market is worth X, so we will capture 1%" is not a demand study. It is an assumption wearing a table.

A study that survives builds from the customer upwards. Retail: how many pass the site, how many stop, what they spend, which competitor loses that sale. Agri-processing: hectares planted within hauling radius, actual yields, the farmgate price. Land development: who the buyers are, what they can pay, and what else sells in the catchment.

That needs primary work — traffic counts, surveys, trade interviews, focus groups, price checks on foot. The ICC wording is precise: the study must identify the supply gaps. If your market study cannot name the competitors and why a customer switches, it is only a market description.

The financial study: the numbers a lender reads

MetricWhat it tells youWhat to watch
Total project costLand, construction, equipment, pre-operating, working capital, contingencyThin contingency; interest during construction omitted
Sources and usesWhere every peso comes from and goesEquity "to be raised" rather than committed
StatementsIncome statement and cash flow by period, with debt serviceProfit in a year the project runs out of cash
NPV and IRRValue created after discounting at the required return; the return the project earnsA discount rate that is borrowed, not justified; an IRR that only works in the base case
Payback and break-evenHow long until the investment is recovered; the volume where losses stopA payback from skipping replacement capital; break-even below practical minimum
DSCRCash for debt service divided by that year's principal and interestAny year near 1.0x, where a small miss is a default
SensitivityWhat happens when costs rise or revenue fallsOne token downside case instead of a range

DSCR is unforgiving: take the cash the project generates in a year, before interest and principal but after tax and working capital, and divide it by what the loan demands. At 1.0x the project pays the bank and nothing else. Lenders want headroom, negotiated per deal and sector, so it lands in the term sheet rather than a textbook. One reference point: IFC and IDB Invest's indicative 2026 term sheet for a solar tender sizes debt to a minimum DSCR of 1.20x under a P90 ten-year case, with a 1.00x floor in a P99 one-year stress case.

Sensitivity is where amateurs stop. The ICC's method is a good minimum: raise costs 10% and 20%, cut revenues 10% and 20%, test the combination. If the project works only in the base case, the study has told you something useful.

On the discount rate, the ICC guidelines make a point worth borrowing: WACC fits only when the project's risk matches the company's business risk and the funding comes from a pool in those proportions. When the project is riskier, the equity viewpoint is more honest. One rate for a new outlet added to an existing chain; a higher one for a first plant on an undeveloped river.

What drives the cost of a study

I have found no published rate card for this work, and no government schedule of fees exists. A figure quoted before scoping is a guess with a letterhead. What can be explained is what moves it.

DriverWhy it moves cost
ScopeEach site or business line needs its own demand work, cost estimate and model line
Primary vs secondary researchTraffic counts, surveys, trade interviews and FGDs cost money and time
Sector complexityA cafe fit-out and a hydroelectric plant are not the same study; energy, agri, manufacturing and land need engineering
Environmental routeAn ECC or EIS is a separate document with its own specialists and sampling
Model complexityA single-outlet cash flow is a spreadsheet; a 20-year model with debt sculpting and tax losses is not
Regulatory layers and revisionsForeign ownership, incentives and registration add sections and advisers; a compressed timeline or a rebuild after the board changes the structure costs more
The readerA bank credit committee needs documented assumptions and a traceable model; an internal go/no-go does not

That last row is the one people underestimate. A bank credit committee wants assumptions documented and the downside tested; your board wants the recommendation and the three risks that would overturn it.

Running retail sites taught me the same lesson: site-level demand work decides whether the model is worth building.

IPAC does not publish peso ranges. We quote per project after scoping, because the honest answer to "how much" is a scope, a schedule and a deliverable list.

How long it takes

A single-site study with available data can be delivered in a few weeks. A multi-site or regulated project, or one needing field research and an environmental submission, runs for months. Four things stretch it: field data collection; engineering inputs such as surveys and quotations; the environmental route; and revisions after review.

The environmental clock matters. DENR rules direct proponents to run the environmental study alongside the feasibility study, and EMB may check by asking for the study's terms of reference and the report. Under Administrative Order No. 42, an ECC for an environmentally critical project is processed within 120 working days, for a non-critical project in a critical area within 60, and a Certificate of Non-Coverage within 15 days. An ECC expires if the project is not implemented within five years, and no clock runs until you file.

The Ease of Doing Business Act caps simple transactions at 3 working days, complex ones at 7 and highly technical ones at 20. The BOI deems an application approved if the Board does not act within 20 working days; PEZA's Board meets twice a month, applications due three working days before.

Why studies get rejected

  • Optimistic demand, no primary research. A share of a market nobody measured. Lenders have seen the curve before.
  • No sensitivity, or one token downside. "What if sales are lower" does not answer 60% capacity for two years.
  • Undocumented capital. "Owner's equity" with no bank statement; a loan in the model that appears in no term sheet.
  • No environmental clearance plan. Operations modelled from early on, the ECC not yet applied for.
  • An unexplained track record gap. Reviewers are not rejecting you for being new, but for not addressing it with a co-sponsor, a sector-experienced hire or a phased entry.
  • Round-number costs and a model that does not tie. Equipment priced off an old catalogue; a summary quoting one IRR while the spreadsheet shows another.
  • A study written for the wrong room. Sent to a bank, built for an internal decision.

Decide who has to say yes and write for that room.

Frequently asked questions

How much does a feasibility study cost in the Philippines? No published rate card exists, and a figure given before scoping is a guess. Cost depends on the sites and business lines, whether primary research is needed, sector complexity, whether an ECC or EIS is required, the model's length, the regulatory layers a foreign investor brings, and the timeline. IPAC quotes per project after scoping.

How long does a feasibility study take? A single-site study with available data can be done in a few weeks. A regulated or multi-site project, or one needing field research and an environmental submission, runs for months.

What is the difference between a feasibility study and a business plan? A feasibility study tests whether the project should exist and may conclude that it should not. A business plan assumes the decision is made and sets out how to execute. Lenders read the first; management runs on the second.

What should a feasibility study for a small business include? Who the customers are and what they pay now; a set-up budget built on quotations, not estimates; a cash flow including debt service; break-even; a downside case. For one outlet that can be short; for a BOI application it cannot.

Does my project need an ECC before I can start? It depends on the category. Environmentally critical projects, and non-critical ones in environmentally critical areas, need an Environmental Compliance Certificate. Projects unlikely to cause significant impact sit outside the system and may secure a Certificate of Non-Coverage. The screening is in EMB MC 2014-005.

Do banks in the Philippines require a feasibility study? It varies by bank, product and borrower. For an existing business, lenders typically ask for three years of audited statements and a business plan. For a new project the substitute is a feasibility study or detailed project description, as the DOST-TAPI I-Tech lending program (funded through LandBank) and DBP's project financing both specify. Expect the bank to test demand and debt coverage, not just read the summary.

Work with IPAC

IPAC can scope a study, build the model and prepare it for the reader who has to approve it. Our Market Research & Analysis service covers demand work and competitor mapping, Business Strategy Development turns findings into a recommendation you can act on, and Financial Advisory & Risk Management builds and stress-tests the model, including the debt schedule a lender picks apart. Still at the structure stage? Read How to Start a Business in the Philippines as a Foreigner (2026 Guide); on land, Can Foreigners Own Property in the Philippines? What the Law Allows in 2026 sets out who may hold what; and if you plan to live here while the project runs, see SRRV Requirements 2026: A Practical Guide to the Philippine Retirement Visa for Foreigners.

Book a free consultation. Mobile: 0917 823 6858 Please text your full name, business name and business location first before calling.

IPAC is a consultancy. It is not a law firm or a government agency, and it does not issue environmental clearances or approve projects. This article is general information, not legal, tax or investment advice for your specific situation.


About the author

Rodel Lacorte, CPA has been a Certified Public Accountant since 1993 and began his career at PwC Philippines (1992–1996). He has since run his own CPA practice, operated five Shell stations as a dealer for 20 years, founded Taza Mia Coffee in 2011, and led hydropower and land-development ventures, including three hydropower feasibility studies. He founded IPAC in 2023. More about Rodel